Electricity & grids guide

Transmission and HVDC Explained: Moving Power Far

How high-voltage lines move power, why losses fall with voltage, when HVDC beats AC, and key links from China's UHVDC to Viking Link and the ASEAN Power Grid.

Updated 6 min read 1,325 words

Power stations are rarely where the people are. Hydropower sits in mountains, the best wind blows offshore, solar is strongest in deserts and coal plants were often built next to mines. Transmission lines join all of it to the cities and factories that use it. They are the least glamorous part of the energy system and, in many countries, the slowest to build. This guide covers how high-voltage transmission works, where the losses come from, why direct current is making a comeback and which projects are shaping grids from Europe to Southeast Asia.

Voltage ladders and why they exist

A generator typically produces power at 10–25 kV. A step-up transformer raises that to transmission voltage, the network carries it across the country, and substations step it down in stages until it reaches homes at 230 V (or 120 V in North America).

Region Common transmission voltages Distribution
Europe 220 kV, 380–400 kV 10–110 kV, 400/230 V
United States 115–230 kV, 345 kV, 500 kV, 765 kV 4–35 kV, 240/120 V
Peninsular Malaysia (TNB) 132 kV, 275 kV, 500 kV 11–33 kV, 400/230 V
China 220 kV, 500 kV, 1,000 kV UHV AC, ±800/±1,100 kV UHVDC 10–110 kV, 380/220 V

The reason for climbing so high is a simple piece of physics. Power equals voltage times current (P = V × I), while resistive loss in a conductor equals I²R. For a given amount of power, a higher voltage means a lower current, and loss falls with the square of that current.

Line loss = I² × R, with I = P / (√3 × V × cos φ) for a three-phase line

Example: 1,000 MW over a line with R = 2.5 Ω per phase, cos φ = 1 At 220 kV: I ≈ 2,624 A → loss ≈ 3 × 2,624² × 2.5 ≈ 51.6 MW (5.2%) At 400 kV: I ≈ 1,443 A → loss ≈ 3 × 1,443² × 2.5 ≈ 15.6 MW (1.6%)

Real lines also lose energy through corona discharge, transformer losses and reactive power flows, but the I²R term dominates. Size a low-voltage cable for the same effect at home scale with the cable size and voltage drop calculator.

How big are network losses?

World Bank figures put global transmission and distribution losses at roughly 8% of electricity output. The spread between countries is wide. Japan, South Korea, Germany and the Netherlands typically sit around 4–6%. Some grids in South Asia and sub-Saharan Africa report 15–25%, a number that includes “non-technical” losses such as theft and unmetered connections. Of the technical part, distribution usually accounts for more than transmission, because low-voltage wires carry high currents over many short lines.

Cutting losses by a percentage point is worth a lot. On a grid producing 100 TWh a year, one point equals 1 TWh, roughly the yearly output of a 120 MW gas plant running at baseload.

Why direct current came back

Thomas Edison lost the 1880s “war of the currents” because, at the time, only alternating current could be transformed to high voltage. Power electronics changed that. Modern converter stations turn AC into high-voltage DC and back again, and DC has three big advantages:

  1. Lower losses over long distances. No reactive power, no skin effect and only two conductors instead of three. An overhead HVDC line loses roughly 3% per 1,000 km, plus about 0.6–1% at each converter station.
  2. Cables. An AC cable behaves like a long capacitor. Its charging current grows with length until, beyond about 50–80 km, it eats most of the cable’s capacity. DC has no such limit, so nearly every long submarine link is HVDC.
  3. Asynchronous links. DC connects grids that are not in step, for example the Nordic system with continental Europe, or Japan’s 50 Hz east with its 60 Hz west.

The catch is the converter stations, which can cost several hundred million dollars each. That creates a breakeven distance, usually quoted at around 600–800 km for overhead lines and 50–80 km for cables. Below that, AC is generally cheaper. The IEA’s 2023 grids report notes that both technologies will be needed at scale.

LCC and VSC converters

Feature LCC (line-commutated) VSC (voltage-source)
Switching device Thyristors IGBT transistors
Largest ratings Up to about 12 GW per link About 2–3 GW per link and rising
Needs strong AC grid Yes No
Reactive power control Needs filters and compensation Built in
Black start, offshore wind No Yes
Footprint Large Compact

LCC dominates China’s ultra-high-voltage corridors. VSC has become the default for offshore wind, interconnectors between countries and future multi-terminal DC grids such as those planned in the North Sea.

  • Changji–Guquan (China, 2019). About 3,300 km from Xinjiang to Anhui at ±1,100 kV, carrying up to 12 GW. China has built dozens of UHV lines to move coal, hydro, wind and solar power from the west and north to the coast.
  • NordLink (Norway–Germany, 2021). 1,400 MW over about 620 km, letting German wind surpluses flow north and Norwegian hydropower flow south.
  • North Sea Link (Norway–UK, 2021). 1,400 MW over about 720 km.
  • Viking Link (Denmark–UK, 2023). 1,400 MW over about 765 km, the longest land and subsea interconnector in the world when it opened in December 2023.
  • SunZia (USA). A planned 3 GW, roughly 880 km HVDC line carrying New Mexico wind to Arizona and California. It spent well over a decade in permitting before construction began in 2023.

Most of these are interconnectors: they let neighbouring markets trade power, share reserves and smooth out weather.

The ASEAN Power Grid and Malaysia

Southeast Asia has talked about a regional grid since the late 1990s. Progress has come link by link. Peninsular Malaysia has long-standing interconnections with southern Thailand and with Singapore across the Johor Strait. Sarawak has exported power to West Kalimantan in Indonesia through a 275 kV line since 2016. In June 2022 the Lao PDR–Thailand–Malaysia–Singapore Power Integration Project began moving up to 100 MW of Lao hydropower across four countries, the first multilateral trade in the region.

Larger plans include a subsea HVDC cable linking Sarawak’s hydropower to Peninsular Malaysia and possibly Singapore, and Singapore’s programme to import about 6 GW of low-carbon electricity by 2035, with conditional licences granted to projects in Indonesia, Cambodia, Vietnam and Australia. The most ambitious of these, Sun Cable’s Australia–Asia PowerLink, would run a roughly 4,300 km subsea cable from the Northern Territory. Sun Cable went into administration in 2023, was taken over by a new investor group and received Australian environmental approval in 2024, but timelines remain uncertain. Follow the regional picture on the ASEAN page and in Energy in Southeast Asia.

The real bottleneck: permits

Steel and cables are not the slow part. Approval is. In Germany, the 700 km SuedLink corridor, meant to carry northern wind power to the south, was switched to underground cable after local opposition and is now expected around 2028, years later than first planned. In the United States, Lawrence Berkeley National Laboratory’s “Queued Up” data showed roughly 2,600 GW of generation and storage waiting for grid connection at the end of 2023, with typical projects spending around five years in the queue. The IEA estimated in 2023 that the world needs to add or refurbish about 80 million km of lines by 2040, roughly the size of today’s entire global grid.

Key points

  • High voltage cuts current, and loss falls with the square of current.
  • Typical grid losses are 4–8% in advanced systems and much higher where theft is common.
  • HVDC pays off on long overhead routes, long cables and links between unsynchronised grids.
  • VSC converters are opening the way to offshore grids and meshed DC networks.
  • Planning and permits, not technology, decide how fast new lines arrive.

Explore where the world’s large power plants sit relative to demand on the power plants map, and see how frequency is kept stable once the power arrives in Grid Frequency and Balancing.

Calculators for this topic

Frequently asked questions

Why is electricity transmitted at high voltage?
Resistive losses in a line rise with the square of the current. For the same power, doubling the voltage halves the current and cuts losses to a quarter. That is why bulk power moves at 132–765 kV and is stepped down near consumers.
How much electricity is lost in transmission and distribution?
World Bank data put global transmission and distribution losses at roughly 8% of output. Well-run grids in Europe, Japan or Korea lose around 4–7%, while some networks in South Asia, Africa and Latin America lose 15–20% or more, partly through theft and unbilled use.
When is HVDC better than AC?
HVDC wins on very long overhead routes (beyond roughly 600–800 km), on submarine or underground cables longer than about 50–80 km, and when linking grids that are not synchronised, including grids running at different frequencies. Below those distances the cost of converter stations usually makes AC cheaper.
What is the longest HVDC line in the world?
China's Changji–Guquan line, completed in 2019, runs about 3,300 km from Xinjiang to Anhui at ±1,100 kV and carries up to 12 GW. It is the highest-voltage and longest-distance HVDC link in operation.
What is the difference between LCC and VSC HVDC?
Line-commutated converters (LCC) use thyristors and are proven at the very highest powers, but they need a strong AC grid at both ends. Voltage-source converters (VSC) use IGBT transistors, can control reactive power, connect to weak grids and offshore wind farms, restart a dead grid and form multi-terminal networks.
Is there a power grid connecting ASEAN countries?
Partly. The ASEAN Power Grid is a long-running plan to link national grids through bilateral interconnections, several of which already operate, including Malaysia with Thailand and Singapore. Since 2022 the Lao PDR–Thailand–Malaysia–Singapore project has traded up to 100 MW of hydropower across four countries.

Sources & references

  1. World Bank: Electric power transmission and distribution losses (% of output)
  2. IEA (2023). Electricity Grids and Secure Energy Transitions
  3. Lawrence Berkeley National Laboratory: Queued Up: interconnection queue data
  4. ASEAN Centre for Energy: ASEAN Power Grid
  5. National Grid: Viking Link interconnector

Figures in this guide are typical ranges drawn from the sources above; your own numbers depend on location, prices and equipment. Use the linked calculators for site-specific estimates.