Under-frequency load shedding (UFLS)

Automatic disconnection of blocks of customer demand when grid frequency falls below set thresholds, to prevent a total collapse.

UFLS relays are a last line of defence. In Continental Europe shedding starts at 49.0 Hz and steps up so that about 45% of load can be cut by 48.0 Hz. Great Britain’s scheme starts at 48.8 Hz; Texas’s ERCOT begins at 59.3 Hz on its 60 Hz grid.

In Britain on 9 August 2019, a lightning strike followed by the loss of a wind farm and a gas plant pushed frequency to 48.8 Hz; UFLS disconnected about 1 million customers for under an hour, but the grid survived. See blackout.

Related terms

All terms →
  • Grid frequency

    The rate at which alternating current changes direction on a power system, 50 Hz or 60 Hz, which reflects the instantaneous balance of supply and demand.

  • Rate of change of frequency (RoCoF)

    How fast grid frequency rises or falls after a sudden imbalance, in hertz per second; lower system inertia means faster changes.

  • Blackout

    A complete loss of electricity supply over an area, from a neighbourhood to an entire country, often after a cascade of failures.

  • Frequency containment reserve (FCR)

    The fastest automatic balancing reserve in Europe, which responds within seconds to stop a frequency deviation from growing.